[object Object]

200 TPH Wet Mix Plant Delivered for Large-Scale Road Infrastructure

We supplied and set up a high-capacity wet mix macadam plant for a leading road contractor in the UAE.

LocationUnited Arab Emirates
Project TypeInfrastructure Development | Road Base Construction
EquipmentAtlas WM 200 Wet Mix Macadam Plant

The Challenge

The client needed a high-capacity wet-mix solution to keep up with continuous road base work on a large infrastructure project.

High Throughput Requirement

The project required a 200 TPH output to stay on schedule and maintain steady base layer preparation.

Integrated Storage Need

The contractor needed a combined storage and water system to keep materials flowing smoothly during production.

Fast Operator Readiness

Fast commissioning, calibration, and operator handover were key to starting site work on time.

The Engineering Solution

Atlas Technologies supplied the WM 200 Wet Mix Macadam Plant, tailored for high-volume road base projects, complete with integrated storage, water system, and commissioning support. The plant's 25-ton silo and 15,000-liter tank ensured uninterrupted operation and steady output. Key spare parts, calibration, and operator assistance were included for quick startup.

The Engineering Solution

Plant & Equipment Supplied

WM-200 Wet Mix Macadam Plant at 200 TPH output, paired with a 25-ton wet mix storage silo, 15,000-litre water tank and essential spare parts package — ensuring uninterrupted production from day one.

Timely Delivery & Installation

The plant arrived on schedule matching the contractor's project start date. Site unloading, mechanical setup, electrical connections and control system calibration were completed within 7–10 days of site readiness.

Calibration & Operator Training

Atlas deployed a mechanical and electrical technician on-site to complete calibration, system commissioning and hands-on operator training — so the crew was production-ready from the first shift.

The Victory

Project Outcomes

200 TPH continuous wet mix output
Reliable road base material production
Successful calibration and trial support
Onsite operator training completed

Performance Snapshot

MetricBeforeAfter
Production CapacityNo active setup200 TPH output
Material StorageExternal dependency25-ton integrated silo
Water HandlingManual arrangement15,000-liter integrated tank
Operator ReadinessUntrainedTraining completed
“Atlas delivered a reliable high-capacity solution that aligned perfectly with our project timeline. The commissioning and training support enabled immediate operational readiness.”

Project Engineer

Road Infrastructure Contractor, UAE

Planning a High-Capacity Road Base Project?

Get in touch with our engineers for wet-mix macadam solutions designed for quick setup and steady site output.

Frequently asked questions.

What capacity was supplied in this project?

+
This deployment involved a 200 TPH wet-mix macadam (WMM) plant for large-scale road base preparation.

What storage systems were included?

+

Did Atlas provide installation support?

+

Was operator training included?

+